Estimation of cost and the amount of production in construction of forest road by combining hydraulic excavator and bulldozer (Case study: Liashisera district, Guilan Province)

Document Type : Research article

Authors

1 M.Sc. Forestry, Faculty of Natural Resources, University of Guilan, Sowme'eh Sara, Iran

2 Associate Prof, Faculty of Natural Resources, University of Guilan, Sowme'eh Sara, Iran

3 Assistant Prof, Faculty of Natural Resources, University of Guilan, Sowme'eh Sara, Iran

Abstract

Using machines such as hydraulic excavator and bulldozer is very common in construction of forest roads, and their costs have a major share from the hourly cost of a road construction project. Therefore, the estimation of production and costs of each apparatus production unit is regarded as a powerful mean for appropriate management and optimum usage of the facilities. In Liashisera district situated in 27th watershed of Amlash, a combination of two machines of hydraulic excavator and bulldozer were used in the road construction due to economic and environmental considerations. Majority of excavation operations were initially carried out by hydraulic excavator, and the bulldozer was used in the final stage to correct the slope and prepare the road bed for pouring sand scattering. The components of daily construction work including useful and useless times, technical and personal delays were assessed by time study technique in various slope categories. The results showed the average of production amounts of two machines in the slope classes of 10-30, 30-50 and 50-70 percent to be 71.23, 61.49 and 87.18 m3/h and 13.31, 20.87 and 12.28 m/h, respectively. Production cost of two machines per useful working hour was shown to be 8267 IRR per m3 and 39325 IRR per m.

Keywords


 
- Abeli, W.S., 1993. Comparing productivity and costs of three subgrading machines. International Journal of Forest Engineering, 5(1): 33-39.
- Amanzadh, B., 1996. The mechanical properties of the soil used in road construction in forestry projects R.K (Talesh). M.Sc. thesis, Gorgan University of Agricultural Sciences and Natural Resources, 158p (In Persian).
- Arefian, R., 1996. Soil mechanical characteristics Ziarat forestry plan and its application in the road. M.Sc. thesis, Gorgan University of Agricultural Sciences and Natural Resources, 75p (In Persian).
- Aruga, K., Sessions, J. and Akay, A.E., 2005. Heuristic planning techniques applied to forest road profiles. Journal of Forest Research, 10: 83-92.
- Behbehani, H., 2009. Road construction, the road geometry. University of Tehran Press, 358p (In Persian).
- Cabezas, W., 1994. Informe finale valuation de equips en La construction de Caminos. Informetecnico Forestal MININCO S.A, Concepcion, FAO, Rome, 37p.
- Chehreghani, S. and Alipoor, A., 2007. Investigation ergonomics status of the transport machinery in the mines. Seventh Safety Conference, Health and Environment in Mines and Mineral Industries, Tehran, 364-370 (In Persian).
- FAO., 1992. Cost control in forest harvesting and road construction. Food and Agriculture Organization of the United Nations, Rome, Forestry Paper, 99: 38-89.
- Johansson, J., 1995. Excavators as base machines in logging operations. International Journal of Forest Engineering, 7(1): 7-17.
- Lotfalian, M. and Parsakhoo, A., 2013. Forest Roads Network Planning. Publications of Aeeizh, Tehran, 168p (In Persian).
- Moeini, M., 2004. Applied algorithm hourly rate analysis of construction equipments. First International Conference of Project Management, Tehran, 16p (In Persian).
- Nagy, M.M., 1978. Productivity and cost of four subgrade construction machines. FERIC Technical Report Vancouver Canada, 28, 50p.
- Nobakht, Sh., 2002. Mapping. No. 114, Published by Islamic Azad University, 464p (In Persian).
- Parsakhoo, A., 2008. Comparison of Bulldozer and Hydraulic Excavator Performance in Constructing the Secondary Forest Roads. M.Sc. thesis, University of Mazandaran,120p (In Persian).
- Parsakhoo, A., Hosseini, S.A., Lotfalian, M. and Jalilvand, H., 2009. Comparing hydraulic  excavator and bulldozer in construction of forest road standard cross section in different slope classes (Lattalar, Mazandaran Province).  Journal of Science and Technology of Agriculture and Natural Resources, 13(47): 397-408 (In Persian).
- Sarikhani, N., 1999. Instructions Forest Road Projects. No. 138, Published by Management and Planning Organization, Tehran, 200p (In Persian).
- Sarikhani, N., 2001. Logging of Forest. University of Tehran Press, Tehran, 776p (In Persian).
- Sedlak, O., 1985. Forest Road Planning, Location and Construction Techniques on Steep Terrain. FAO Forestry Paper, FAO, Rome, 333p.
- Winkler, N., 1998. Environmentally Sound Road Construction in Mountainous Terrain. Forest  Harvesting Case-study 10, FAO, Rome, 64p.